← All projects

CASE 02 / Water supply

Water supply automation for two pumping stations

Two water supply complexes operate independently with the interconnection valve closed. PR205 controllers manage tank filling from both wells and maintain pressure at pumping station 1.

Project stageCompleted
Personal contribution

Electrical design, PR205 programs for both wells and pumping station 1, and commissioning

Technologies
OWEN PR-205Vemper VR100PI controlsPlan 84–20 mA0–10 V
2water supply complexes
6storage tanks
3PR205 controllers in scope
One of the two pumping stations. The cabinet on the right houses the operator controls, and two variable frequency drives are mounted on the left.
Problem

Automate storage tank filling and stabilize discharge pressure at pumping station 1.

Solution

Two PR205 controllers manage tank filling from the wells. A third regulates pressure and stages pumps at station 1.

Outcome

The system entered service and supplies water automatically to production and site service facilities.

Interactive water supply system

Interactive demonstration model. Parameters and timing are illustrative. Not intended for equipment control.

Simulation controls

Ready to start
Model time 00:00.0
1.5 model units/s

Raise demand to bring the second pump online.

Model pressure / setpoint
0 / 3 bar
PI output
0%
Well 1
Idle
Well 2
Idle
Complex 1 storage
32%
Group A
39%
Group B
24%
Pump 1
Stopped
Pump 2
Stopped

Complex 1

Well 1 Idle OWEN PR205 Well control Fill valve Closed Complex 1 storage 1.1 32% 1.2 32% Pumping station 1 OWEN PR205 PI control Vemper VR100 0 Hz Vemper VR100 0 Hz Pump 1 Stopped Pump 2 Stopped Complex 1 network Pressure 0 bar

Complex 2

Well 2 Idle OWEN PR205 Well control Valve A Closed Valve B Closed Group A A1 39% A2 39% Group B B1 24% B2 24% Pumping station 2 Third-party automation Complex 2 network
Complex 1 network Complex 2 network
Pipe Active flow Control signal

Connected tanks share one level at each step. Level is proportional to stored volume. Well 2 flow splits equally when both branches are open.

Well 2 filling sensors

If a sensor fails or its reading is invalid, its group’s fill valve opens. Continued filling can cause overflow. The model’s booster protection uses the physical level independently of these sensors.

Measured level
39%
Physical level
39%
Fill valve
Closed
Overflow
0 model units/s
Volume spilled
0 model units
Measured level
24%
Physical level
24%
Fill valve
Closed
Overflow
0 model units/s
Volume spilled
0 model units

Equipment

Well 1

Supplies the connected tank pair in Complex 1. A dedicated PR205 controls filling.

Event log

Start the model to see events.

    Scale 4–20 mA to pressure or level →

    Problem and constraints

    Production and associated facilities needed an automatically controlled water supply. The original installation relied on an operator to start the pump and switch valves. Increased consumption required a second well and pumping station.

    There is no direct communication link between the stations. In the configuration shown, the interconnection valve is closed and each complex serves its own network. The controls needed to support autonomous operation and local pump redundancy.

    Project objective

    Automate storage tank filling from both wells. Maintain pressure at pumping station 1 with pump staging and redundancy.

    My responsibility

    I was responsible for automation of both wells and pumping station 1. My scope covered requirements, equipment selection, electrical schematics, I/O definition, three PR205 programs, VFD configuration, PI tuning, functional checks and commissioning. I produced the electrical documentation in sPlan 8.

    This describes my automation scope. Well construction and mechanical pump maintenance are outside the personal contribution claimed here.

    System architecture

    Each complex has a well, storage tanks and a pumping station. The interconnection valve is closed. The complexes exchange neither water nor data.

    In Complex 1 a dedicated OWEN PR205 fills two connected tanks through a common valve. The valve opens at the low level setpoint and closes at the high level setpoint. A second PR205 maintains pressure at station 1 and controls two Vemper VR100 variable frequency drives.

    In Complex 2 a PR205 controls filling of two connected tank pairs. Each group calls for water independently. Both valves open when both groups call for water. When a group reaches its high level, its branch closes while the other can continue filling.

    Pumping station 2 — automated by a third party.

    Pressure control, sequencing and rotation at station 1

    Pressure control uses proportional and integral action without a derivative term. The loop is: pressure setpoint → PI controller → frequency reference → pump speed → measured pressure.

    When one pump remains at its output limit without meeting demand, a time-qualified condition starts the second pump. Both drives then receive a common reference from one PI controller. When demand falls, one pump stops after a delay to avoid responding to brief fluctuations.

    Duty rotation accounts for accumulated running hours. The incoming pump starts before the outgoing pump stops. I adjusted the overlap during commissioning against the actual pressure response to obtain a smooth transition. Site-specific thresholds and delays are not disclosed here.

    What commissioning revealed

    Surface ripples caused brief fluctuations in the hydrostatic level signal. I applied filtering and required the low-level condition to persist before accepting it.

    I tuned the PI loop using the actual plant response. When oscillation appeared, I reduced proportional gain and adjusted integral action. I checked responses to setpoint changes in both directions rather than only observing one steady operating point.

    Functional checks and standby operation at station 1

    I checked installation against drawings, circuit continuity, cabinet power, I/O, transmitters, valves and drives before trial starts and automatic operation. An incorrect pump rotation direction was corrected in the VFD configuration.

    The commissioning account records checks of low and high levels, pressure and level signal loss, drive faults, emergency stop and standby pump starting. Analogue signal loss was tested by disconnecting the relevant 4–20 mA circuit.

    A VFD fault excludes the affected pump and starts the standby unit while pressure control continues through the healthy pump. Restarting the previously faulty pump requires manual confirmation. Shutdown causes are handled separately. These are described process functions; no certified safety integrity level is claimed.

    Documented outcome

    The system entered service and supplies water automatically to production and site service facilities. With the valve closed, the complexes operate independently. The wells replenish storage on demand. Pumping station 1 maintains pressure, stages its pumps and provides local redundancy.

    An operating pump failure is described in which the programmed standby function started the healthy unit and maintained pressure control. My contribution was the redundancy logic; I did not diagnose the pump’s mechanical failure.

    No quantified savings, guaranteed failure-free period or measured regulation accuracy is claimed. Public test records and measured trend data have not been supplied.

    Physical limits and engineering lesson

    Automation cannot make up a water deficit when well yield is lower than consumption. I added a level display graph to support analysis of inflow and demand. It improved visibility of the process without removing the source limitation.

    The key design decisions were autonomous control with the valve closed, local pump redundancy and level signal filtering.

    ← All projects